Construction Update - Griffiths Teas

Construction Update

13 March 2017

Here's the latest news regarding one of Surry Hill's grandest warehouse conversions.

Construction works are progressing well and are largely on program after making adjustments for inclement weather and are forecast to be complete by mid September 2017.

Structural works and floors within the building are complete up to and including Level 7 with only the mezzanine, roof steel and roof sheeting remaining for the building to be largely watertight.

Remediation of window openings and replacement of external windows are also progressing well and have advanced to Level 6.

The internal walls have been constructed up to Level 5 and the roughin of services is also progressing on these levels.

Below are some progress photographs.