Shoreline - Manly Beach

Construction Update

25 March 2019

 

Construction Update: Shoreline

As we approach Easter, we are excited to share with you the progress that has been achieved by the team during the start of 2019.

 

Since the last update in December 2018, we have completed the following key milestones:

• The concrete framed structure of the building is now substantially complete with only the roof slab remaining to be cast. 

 

• Installation of the precast concrete façade for the entire project is complete.

 

• Fabrication of the roof structural steelwork is underway off site, and will be delivered to site early April.

 

• We have commenced the internal services rough-in and construction of internal wall framing to your homes, commencing on the Ground Floor.

 

• The basement carpark has been stripped out of formwork and the team are well into the installation of high level services (power, lighting, carpark ventilation).

 

• Painting is also underway to the carpark areas and building services plant rooms are being constructed.